With Hobbs Hollow finished in Brown County State Park we will move our 2018 volunteer trail building efforts back into Yellowwood for 2018. The goal is to finish the Crooked Creek Trail in time for the 2018 Brown County Epic. This is a pretty big goal, as we have 2.5 miles of trail to build through very rugged terrain.
So we are going to have trail building weekends the first full weekend of each month.
Jan 13/14 Feb 3/4 March 3/4 April 7/8 May 5/6 June 2/3 July 7/8 Aug 4/5 Sept 8/9 Oct 6/7 Nov 3/4 Dec 1/2 Here is a map showing the plan. The Yellow section is pin flagged and ready to build. The orange section has the corridor taped and is ready for State Forests to review. The white section needs field work to finish layout. When finished it will be about a 5 mile rugged back country loop. Also the goal is to bring the crooked Creek Trail down to the Lake, allowing the Hoosier Half Pipe to be its own trail section.